Enam Essence

Bali infrastructure projects 2026–2029: rail, roads and the Bukit

Short answer

The project that matters most for the Bukit is already being built: the first 10.89 km of Badung's Southern Ring Road, from Jimbaran towards Uluwatu through Pecatu, broke ground on 27 July 2026 and is due to be finished by the end of 2027. Rail is further off. The airport to Canggu line is now an agreement for a battery tram, with groundbreaking planned for March 2027 and no financing announced. The toll road to the west of the island has been cut in half and will not open before 2031.

Aerial view of the six Enam Essence homes among the trees in Pecatu, Uluwatu, Bali
The six homes from above, among the trees in Pecatu. Render.

Where each project stands, November 2026

Bali has a long list of announced projects and a shorter list of projects being built. The table separates them. Each row has a source at the end of the page.

ProjectStageNext date given
Southern Ring Road, first stage (Jimbaran to Uluwatu, 10.89 km)Under construction since 27 Jul 2026Completion targeted end of 2027
Pecatu to Uluwatu traffic schemeIn force since 2 Jul 2026None; it is permanent
Jimbaran underpassApproved and budgeted; no contract award reportedConstruction planned for 2026 to 2027
Battery tram, airport to Canggu (about 12 km)Cooperation agreement signed 1 Sep 2026; studies; financing not announcedGroundbreaking planned Mar 2027; full line 2029
Underground line from 2024Broke ground in 2024, never built; no investorNone
Gilimanuk to Mengwi toll road (cut to about 42 km)Not under construction; new tender to comeTender from 2027; opening target 2031
Ngurah Rai airport terminal worksUnder construction in 2026No completion date given
North Bali airport (Kubutambahan)In the national plan; studies approvedNo construction start set
Benoa marinaFirst two docks open (up to 75 yachts)Up to 188 yachts and cruise berths, full operation targeted end of 2028

The Southern Ring Road near Uluwatu

Traffic on the Bukit squeezes through a few junctions: the Udayana junction, GWK and Pecatu. Badung regency's answer is a new road, the Southern Ring Road (Jalan Lingkar Selatan). Its first stage runs about 10.9 km from Jimbaran towards Uluwatu through Pecatu Graha, Jimbaran Hijau and Labuan Sait, with a new junction at Siligita. The road is planned at 24 meters wide with 3-meter sidewalks.

Work started on 27 July 2026 in Pecatu, and the regency targets completion by the end of 2027. It costs more than Rp 2.9 trillion, mostly a loan from the state infrastructure financier PT SMI (Rp 2.4 trillion) plus Rp 511 billion of Badung's own revenue. The full ring road is planned at 29.95 km; the remaining sections have not started.

For a buyer, a new road works two ways. It can shorten trips once it opens, and it brings two years of construction and, later, more traffic to the plots next to it. Ask where the route runs relative to the villa you are looking at.

Traffic on the Bukit today

Since 2 July 2026 a permanent traffic scheme governs six junctions on the Pecatu to Uluwatu road, after a month of trials. Among other changes, some right turns are banned in the evening peak, from 5 pm to 10 pm. Closer to the airport, an underpass at the Jimbaran junction has been approved at about Rp 350 billion, but no contract award had been reported by November 2026.

In June 2025 the governor said congestion would be eased by 2028 if four new underpasses in and around Denpasar went to plan; later statements moved the date for the island's road works to 2029. Until then, time the drives that matter to you, at the hours you would make them.

Aerial view of Enam Essence and the neighbouring villas in Pecatu, Uluwatu
The homes and the neighborhood around them, from above. Render.

Rail: from an underground line to a tram plan

In September 2024 an underground line, planned to link the airport, Kuta, Seminyak and Canggu, broke ground at Kuta. It was never built. In April 2026 the transport minister said no investor had come forward.

On 1 September 2026 the province, Badung regency and KAI, the state railway company, signed an agreement to develop a battery-powered tram of about 12 km from the airport to Canggu instead. The plan is groundbreaking in March 2027, a first section in 2028 and the full line in 2029. Before work can start, the tram needs a governor's regulation, technical studies and consultation with the villages on its route. Its cost and financing have not been announced, and in September the transport minister urged that it should not stay on paper.

The toll road to the west

The Gilimanuk to Mengwi toll road, meant to link Bali's western ferry port with the south, was cut from about 96 km to about 42 km, between Pekutatan, Soka and Mengwi, because too few investors were interested. The government plans to look for a builder again from 2027 and targets opening in 2031. It does not touch the Bukit, but it would change travel between the south and the west of the island.

Airports and the marina

At Ngurah Rai, terminal works in 2026 aim to raise capacity to 32 million passengers a year, with a new international departure pier and a bridge between the terminals. A second airport in north Bali, at Kubutambahan, is in the national plan for 2025 to 2029, with studies approved and private financing sought, but no construction date.

In Benoa harbor, the first two docks of a new marina opened in July 2026 for up to 75 yachts. The government plans up to 188 yachts and berths for cruise ships, with full operation targeted for the end of 2028.

Water on the Bukit

The Bukit is limestone with little surface water, and supply is a known issue: in January 2026 Bali Post reported a clean-water shortage in Pecatu. In August 2026 Badung's water company connected an undersea pipe that brings water to south Badung into its network; full operation has not been confirmed. For any villa on the Bukit, ask where the water comes from and what happens in the dry season.

At Enam Essence

Our six homes in Pecatu have their own deep well, more than 200 meters deep, and a water reserve of over 20 m³. We are the developer, so read this as our description; the homes and prices are in the villa guide.

What this means if you are buying

  • Judge a location by what exists and what is being built with a date, not by announcements.
  • For a plot near the new ring road, ask about the route, the construction period and the traffic it will bring.
  • Until the tram and the underpasses exist, the drive to the airport depends on the hour. Time it yourself.
  • On the Bukit, check the water supply of the exact villa.

The area itself is covered in our guide to Uluwatu and the Bukit, and the rules and visitor numbers in the 2026 market guide.

Questions buyers ask us

Is there a train or metro in Bali?
Not yet. An underground line broke ground in 2024 but was never built, and in April 2026 the transport minister said no investor had come forward. In September 2026 the province, Badung regency and the state railway company KAI agreed to develop a battery tram from the airport to Canggu instead, with groundbreaking planned for March 2027. Its financing has not been announced.
Is the road to Uluwatu being improved?
Yes. The first 10.89 km of Badung's Southern Ring Road, from Jimbaran towards Uluwatu through Pecatu, has been under construction since 27 July 2026, with completion targeted for the end of 2027. Since July 2026 a permanent traffic scheme also governs six junctions on the Pecatu to Uluwatu road.
When will the Gilimanuk to Mengwi toll road open?
Not before the end of the decade. The project was cut from about 96 km to about 42 km between Pekutatan and Mengwi, the search for a builder is planned to start in 2027, and the government's target for opening is 2031.
Is Bali building a new airport?
A north Bali airport at Kubutambahan is in the national plan for 2025 to 2029, but no construction start has been set. At Ngurah Rai, the existing airport, terminal works under way in 2026 aim at a capacity of 32 million passengers a year.
Should I pay more for a villa because a road is planned nearby?
Base your decision on what exists and what is actually under construction, with a date. Announced projects in Bali have slipped before: the underground line that broke ground in 2024 is still unbuilt.

Sources

  1. Detik Bali, groundbreaking of the Southern Ring Road, segment 4, Kuta Selatan. 27 July 2026: about 10 km Jimbaran to Uluwatu, Rp 2.9 trillion, target end of 2027
  2. Bali Post, Badung breaks ground on the Southern Ring Road. 27 July 2026: first stage 10.89 km with the Siligita junction, 2026 to 2027; 29.95 km planned in total
  3. Detik Bali, Pecatu to Uluwatu traffic scheme made permanent. 2 July 2026
  4. Kompas, Jimbaran underpass approved. 7 January 2026: about Rp 350 billion
  5. Antara Bali, province and KAI to develop a battery tram, airport to Canggu. Agreement of 1 September 2026; groundbreaking planned March 2027, full line 2029
  6. Investor Trust, transport minister on the Bali tram. 15 September 2026: still at study stage; investor not yet determined
  7. Okezone, transport minister: no investor for Bali rail. 8 April 2026
  8. Katadata, Bali's public transport plans: subway replaced by a tram and water taxis. 10 August 2026: the 2024 underground project not built
  9. Detik, Bali's longest toll road cut to 42 km. 5 June 2026: Pekutatan to Soka to Mengwi
  10. Kontan, Gilimanuk to Mengwi toll: new tender in 2027, operation target 2031. 9 April 2026
  11. Kompas, the governor on new roads and four underpasses. 29 June 2025: underpasses in Denpasar expected by 2028 if all goes to plan
  12. Antara Bali, the governor: all infrastructure works finished by 2029. 2026 statement moving the date to 2029
  13. Detik Bali, Benoa port to become a marina for 188 yachts. 21 July 2026: full operation targeted for the end of 2028
  14. Republika, new marina at Benoa ready for 75 yachts. 27 July 2026: first two docks open
  15. Detik, airport upgrades including Ngurah Rai. 18 June 2026: capacity aim of 32 million passengers a year
  16. Detik Bali, north Bali airport planned for wide-body aircraft. 6 August 2026: no construction start set
  17. Bali Post, south Badung undersea water pipe connected. 4 August 2026
  18. Bali Post, clean water shortage in Pecatu. 7 January 2026